After many engineer meetings some on site demolition and investigative work is performed.
2
Demolition and excavation is performed as per structural and geotechnical requirements for Pile installation.
3
Helical Piles are installed. Axial Pile are installed with standard Under Pinning Brackets and Battered (Tie back) anchors are installed as well.
4

Back fill, Perimeter drainage and rain water leader systems are installed in solid PVC pipe.

5
Shoring detail is erected to support the deck during construction of Column support. The deck contained a concrete topper and also carried a roof load.
6

A Grade Beam is installed to accommodate axial and tension concerns for the column loads.

7
Columns are installed post back fill and compaction. Grade is set and slab construction is underway.
8

Concrete is poured and finished as per home owner specifications.

9
Concrete is cured and railings are installed.
10
Clean and tidy site, finish yard work and other minor landscaping as required.

Advantages of Helical Piles

Screw Piles or Helical Piling is the most cost-effective solution available. It eliminates the need for extra expenditures on soil mining and transportation. Helical Piling technology is used on all site conditions, making it ideal for residential and commercial construction projects.

More Helical Pile Projects

TRUST THE FOUNDATION PROS

Contact Team Foundation Systems Specializing in solutions for homes, light commercial & industrial buildings, electrical and transmission facilities.

Kelowna Foundation Company
Helical Piles Kelowna
Helical Pile (Left) and Helical Extension (Right)

How Can We Help?

Get in touch and ask us anything.

"*" indicates required fields

Name*

SECURE FORM | PRIVACY POLICY

CHANCE® Certified Installers

Team Foundation Systems is a CHANCE® Certified Installer. Save time and money and get the job done right.

Chance Certified Installers Kelowna